Supreme Court dismisses First Nation's appeal of Enbridge Line 9 Reversal

The Supreme Court of Canada released its decision today in the Chippewas of the Thames First Nation (COTTFN) appeal of the National Energy Board ("NEB") approval of the Enbridge Pipelines Inc. Line 9 Reversal Project.  The Court has dismissed the appeal on the basis that a federal board or tribunal can, under certain conditions, provide the process through which the federal Crown discharges its duty to consult with First Nations.  In this particular case, the Court found that the NEB process, in which the COTTFN participated, was sufficient to discharge the Crown's duty.

Read the decision at: COTTFN v. Enbridge and NEB et al.

Tuesday, April 25, 2017

Court grants injunction to Enbridge over interference with maintenance digs

Back in March, 2017, Enbridge Pipelines Inc. ("Enbridge") was in court seeking injunctions against two individuals to prohibit them from interfering with maintenance work being conducted on Lines 10 and 11, two adjacent oil pipelines near Hamilton, Ontario.  Enbridge asserted that the individuals had been regularly interfering with its work crews since January, 2017, including the tearing down of snow fences and gates and verbally demanding that work be shut down.  Enbridge also alleged that, after two weeks of obstruction, the individuals placed rabbit traps to obstruct access to the dig sites and then asserted treaty hunting rights.

In their defence, the individuals involved in the case alleged that they are Haudenosaunee citizens with the ability to exercise rights upon Haudenosaunee traditional treaty territory.  They served Notices of Constitutional Question stating their intention to question the constitutional validity of the following: 1) the Trespass to Property Act as it may apply to a Haudenosaunee person undertaking harvesting activity pursuant to treaty rights; 2) any interim or interlocutory injunction which would directly or indirectly impair, infringe and/or interfere with the exercise of treaty rights where the Crown has not discharged its obligations to uphold the Honour of the Crown (duty to consult and accommodate); and, 3) the granting of any easement (i.e. Enbridge's pipeline easements) where treaty rights would be impaired, infringed and/or interfered with where the Crown has not discharged its obligation to uphold the Honour of the Crown (duty to consult and accommodate).

Justice Broad of the Ontario Superior Court of Justice reviewed the constitutional arguments and concluded that, "the question of whether the Crown has made efforts to comply with its duty to consult and accommodate is not relevant to the exercise of the court's decision to deny an injunction sought by a private party such as Enbridge with an interest in land on discretionary grounds."  Also, Justice Broad noted, "The defendants have been unable to point to any cases where a precondition involving the exhaustion of efforts to consult and find negotiated or legislated resolutions has been recognized or applied where an injunction is sought at the instance of a private property owner where aboriginal treaty rights are claimed or exercised."

Having disposed of the constitutional issues, Justice Broad reviewed Enbridge's request for injunctive relief on the basis of the standard three-part test for injunctions:

1)      the plaintiff must establish a serious question to be tried;
2)      the plaintiff must show that it will suffer irreparable harm if the injunction is not granted; and
3)      the balance of convenience favours the granting of an injunction. This involves a consideration of which party will suffer greater harm if the injunction is granted or refused.
Justice Broad ruled in favour of Enbridge on all three parts of the test.  With respect to the defendants' treaty right claims, he concluded: "The defendants' claim to relevant interests or rights may be advanced by appropriate parties or groups having the requisite standing through lawful avenues.  The defendants' resort to unlawful self-help should not, however, be countenanced ...".

Read the decision at: Enbridge Pipelines Inc. v. Williams et al.

Tuesday, January 31, 2017

Enbridge Line 10 Replacement Pipeline: Landowner intervention persuades Enbridge to rethink pipeline route

The National Energy Board ("NEB") has approved the application by Enbridge Pipelines Inc. for the Line 10 Replacement Pipeline Project.  Line 10 is an oil pipeline that has operated in the Hamilton, Ontario area since the 1960's.  Enbridge also operates Line 11 adjacent to Line 10 within a shared easement.  Late in 2015, Enbridge applied to the NEB for permission to replace Line 10 in large part to avoid increasing integrity issues with the pipe.  Enbridge's proposed replacement pipeline would require less intervention and would also be larger in diameter than the existing pipeline.

For the majority of the replacement pipeline, Enbridge proposed to follow its existing Line 10 / Line 11 corridor; the existing Line 10 would be decommissioned in place and a new pipe would be installed next to it.  However, in certain locations, Enbridge asked for permission to move away from its existing pipeline corridor and to build the replacement pipeline within a new corridor to be established on previously unaffected properties.  Those locations that Enbridge wanted to avoid were golf courses.

In its application to the NEB, Enbridge suggested that it was necessary to route its replacement pipeline through previously undisturbed farm land because by doing so it would minimize the environmental and socio-economic impacts of its project.  In other words, Enbridge took the position that creating a new pipeline corridor through previously undisturbed agricultural lands would cause less impact than constructing and operating its pipeline through golf courses that already accommodated Enbridge's existing two-pipeline corridor.  

Landowners in the vicinity of two of the golf courses along Enbridge's existing Line 10 corridor challenged Enbridge on its theory.  They joined together and formed the Copetown Landowners Group ("CLG"), and intervened in the NEB hearing process.  CLG engaged an expert in pipeline routing and land use planning and submitted lay and expert evidence to the NEB that demonstrated the obvious - creating a new pipeline corridor through previously undisturbed farm land in order to avoid disturbing previously disturbed golf courses (which would still, in any event, house the operational Line 11 and the decommissioned Line 10) would not minimize the environmental and socio-economic impacts of the project.  

Ultimately, Enbridge revisited its proposed pipeline route in the area where it had intended to construct the replacement pipeline across lands owned by CLG members.  Enbridge still did not choose to install the replacement pipeline adjacent to its existing Line 10 and Line 11 pipelines, but it did adjust its route to follow another nearby utility corridor (one that actually was located between the existing Enbridge corridor and its proposed corridor through the CLG-owned lands).  The nearby utility corridor was already home to an electrical transmission line and multiple underground pipelines.

CLG's participation in the NEB Line 10 hearing demonstrates the importance of landowner involvement in the project approvals process.  But for the intervention of the CLG landowners, it is unlikely that Enbridge would have adjusted its proposed route to follow an existing previously-disturbed corridor.  Enbridge wanted, for its own reasons, to avoid installing its replacement pipeline through golf courses.  Enbridge was determined to create a new pipeline route through previously undisturbed farm land.  And in the absence of any opposition, it is unlikely that the NEB would have questioned the proposal, even though it would create a third utility corridor through prime farm land. 

Landowners have to be ready to participate in the regulatory process to protect their interests and the interests of their communities.  It seems that no one else, including local municipalities, will do it for them.

Read the NEB's decision at: NEB Line 10 Replacement Decision.

Thursday, June 30, 2016

Federal Court of Appeal overturns Northern Gateway approval

The Federal Court of Appeal has quashed the decision by the Federal Cabinet to approve the Northern Gateway pipeline project on the basis that Canada failed to consult adequately with First Nations on the pipeline route.  With changes to the National Energy Board Act made by the previous government, pipeline projects like the Northern Gateway project are subject only to a review by the National Energy Board.  The NEB then makes a recommendation to the Federal Cabinet, which has the ultimate say in whether a project is approved.

The appeal court ruled that Canada failed in its approach to consultation with First Nations on the project, noting that the government carried out consultations in a "brief, hurried and inadequate" way.

Read the decision at: Federal Court of Appeal.

Tuesday, December 22, 2015

COTTFN files for leave to appeal to the Supreme Court in Enbridge Line 9B case

In October, I posted about the Federal Court of Appeal decision to deny an appeal by the Chippewas of the Thames First Nation ("COTTFN") from the decision of the National Energy Board ("NEB") approving the Enbridge Line 9B Reversal and Line 9 Capacity Expansion Project application.  COTTFN has now filed an application for leave to appeal the Federal Court of Appeal's decision to the Supreme Court of Canada.  Given that there was a dissenting opinion from one of the FCA judges and that the subject matter of the appeal concerns the role of administrative tribunals in relation to the Crown's duty to consult with and accommodate First Nations, there would seem to be a good chance that leave will be granted.

Thursday, October 29, 2015

Federal Court of Appeal split on Chippewas of the Thames appeal of NEB Line 9B Decision

In a split decision, the Federal Court of Appeal has dismissed the appeal of the Chippewas of the Thames First Nation of the National Energy Board's approval of Enbridge's Line 9B Reversal and Line 9 Expansion Project.  At issue in the appeal was the Federal Crown's duty to consult with First Nations - was the NEB required as part of its decision-making process to determine whether the Federal Crown (which was not a party to the NEB process) was under a duty to consult First Nations with respect to potential adverse impacts of the proposed project and, if so, whether it had adequately discharged that duty?

Ryer, J.A., writing for the majority of the Court in dismissing the appeal, found that that the NEB was not required as a precondition to its consideration of Enbridge's application to determine whether the Federal Crown was under a duty to consult (or whether it had discharged that duty) because the Federal Crown was not a participant in the Enbridge application.  Justice Ryer noted that, if the Crown had appeared before the NEB, these issues could have been argued.  However, the Federal Crown did not participate in the NEB approval process.

Justice Ryer then went on to consider whether the NEB itself has the power to undertake and discharge the duty to consult with First Nations on behalf of the Federal Crown.  He noted that it is within the power of Parliament to require the NEB to discharge the Crown's duty to consult, but it has not done so by legislation.  He questions how the NEB could both carry out the duty to consult and then adjudicate on whether or it had adequately discharged the duty.  Yet, in a letter sent by the Minister of Natural Resources concerning the Enbridge project, the Minister suggested that the Federal Government "relies on the NEB processes to address potential impacts to Aboriginal and treaty rights stemming from projects under its mandate."

Nevertheless, Justice Ryer concluded that there was no delegation of the duty to consult by the Federal Crown to the NEB.  Therefore, any shortcoming in the NEB's consultation with First Nations could not stand as a reason for setting aside its decision to consider Enbridge's application and, ultimately, to approve it.

Justice Rennie of the Federal Court of Appeal provided a dissenting opinion on the case.  His opinion was that the Supreme Court's 2010 decision in Rio Tinto Alcan Inc. v. Carrier Sekani Tribal Council meant that it was not necessary for the Federal Crown to be a party to the NEB proceeding in order for the NEB to be required to rule upon the Crown's duty to consult.  He viewed that decision of the Supreme Court as changing the law on the duty to consult.  As a result, Justice Rennie's opinion was the NEB must review the duty to consult in the context of a Section 58 application (like the Enbridge Line 9B application, which is not subject to final approval by the Federal Cabinet):

The Board must have, and exercise, the power to assess whether the duty to consult has been fulfilled, and to refuse to grant an approval if there is an unfulfilled duty to consult; otherwise the section 58 regime allows for the approval of projects which may adversely affect Aboriginal rights without the Crown ever consulting with the Aboriginal group in question. A project proponent can apply, go through the NEB's hearing process, and receive approval. The Crown can remain silent, on the sidelines. No consultation with the Crown need occur at any point. Indeed, the Crown lacks the statutory authority to prevent an application from being approved by the Board, even if it should want to.

Rennie, J.A. concluded that the NEB should have considered whether there was a duty to consult and, if so, whether it had been fulfilled.  And the NEB should only have granted approval to Enbridge if there was no unfulfilled duty to consult with First Nations.  Justice Rennie would have allowed the appeal.

Given the split in the Federal Court of Appeal on this appeal, this may very well be a case that will be heard by the Supreme Court of Canada.

The full text of the Federal Court of Appeal decision is available at: 2015 FCA 222.

Friday, September 19, 2014

It looks like Enbridge is back in Court today looking to extend its injunction against Line 9 protesters

I have recently written about Enbridge Pipelines Inc.'s efforts to obtain injunctions against Line 9 protesters (click here).  It looks as if Enbridge is back in Court in London today in what is likely a motion for an extension of the injunction already obtained against protesters a few weeks ago.  If you're interested in observing the motion proceeding, the court docket says it will be heard by Madam Justice Gorman at 2:30 p.m. in Courtroom 14 on the 7th Floor of the London Courthouse at 80 Dundas Street.

Wednesday, August 13, 2014

Court grants injunction to Enbridge, but is concerned about the right of protesters to be heard

The Ontario Superior Court of Justice recently granted a temporary injunction prohibiting unauthorized persons from entering or occupying an Enbridge Pipelines Inc. valve installation site in Innerkip, Ontario, near Woodstock.  On August 5, 2014, 25 or so individuals had entered the Enbridge work site, occupied it and then refused to leave.  Enbridge brought an ex parte motion for orders requiring the protesters to leave.

The valve installation work is being required by the National Energy Board (NEB) as part of the Line 9 oil pipeline reversal project, and Enbridge alleged that the work is time-sensitive - there is no time to waste in getting the protesters off the site.  Enbridge's evidence provided: "A project of this magnitude involves the organization and deployment of extensive resources and expertise.  The timing and execution of the project cannot be dictated by persons who do not understand or respect Enbridge's safety and operational protocols.  Enbridge cannot proceed with the required and time-sensitive Valve Installation with Trespassers on the site."

In reviewing the motion (in which the only party present was Enbridge), Justice E.M. Morgan commented:

While property rights and economic interests are important in the Canadian legal system, so are rights of expression. I agree that the time, place, and manner of expression can be tempered by competing rights, see Committee for the Commonwealth of Canada v Canada, 1991 CanLII 119 (SCC), [1991] 1 SCR 139, and that generally “[p]ersons are free to engage in political protest of that public nature, but the law does not permit them to do so by engaging in civil disobedience through trespassing on the private property of others…” Canadian National Railway v Chippewa of Sarnia First Nation, 2012 ONSC 7348 (CanLII), 2012 ONSC 7348, at para 23. Nevertheless, there must be some reason other than the unilateral claim to property rights to deprive otherwise non-violent protesters the right to be heard.
 
Here there is an economic imperative to the timing of the motion, but there is no safety imperative that created the short timeline and that made notice of the Application impossible. The valve installation has a safety motivation as evidenced in the National Energy Board report, but that is a long term concern due to the upcoming changes in the oil flow, not an immediate one.

Justice Morgan questioned Enbridge about why it had not given notice of its motion to the protesters, given that there was not safety imperative involved.  Enbridge explained that it is faced with adversaries that are difficult to identify - a "shifting group of individuals".  In the end, Enbridge was granted its injunction to permit the expulsion of the protesters, but for a duration of only 10 days.  After 10 days, Enbridge would have to return to the Court either in London or in Woodstock (not in Toronto, where the original motion was heard) to extend the injuction on at least 3 days' notice to the protesters.

With respect to the right to be heard, Justice Morgan stated: "It is important that the protesters’ right to be heard be a realistic one, and that notice of a new hearing date either be disseminated before the protesters disband or be announced in a way that is likely to come to their attention. It is not the purpose of an ex parte injunction to stall the proceedings so that the Applicant’s opponents fade away without being heard in court."

Read the decision at: Enbridge Pipelines Inc. v. Jane Doe.

Wednesday, July 23, 2014

Enbridge wants land to build replacement pipeline; Landowner refuses because no construction agreement in place; NEB gives Enbridge right to use land; Enbridge makes a huge mess; NEB issues stop work order - Why was Right of Entry granted in the first place?


The National Energy Board (NEB) has recently issued a stop work and compliance order to Enbridge Pipelines Inc. in connection with Enbridge's Line 3 Replacement project on a Manitoba farm property.  The Line 3 project is similar to the Line 6 replacements that took place in Michigan following the Marshall, MI rupture a few years ago - Enbridge leaves a rotting pipeline in place and takes more land to build a new line nearby. 

In this case, Enbridge was not able to obtain the land it needed from the landowner by agreement.  Enbridge then turned to the NEB for the right to take the land it needed for its new pipeline.  In fact, Enbridge appears to have made 25 applications for right of entry to the NEB, all of which were granted in spite of objections by many affected landowners.  The bases for the landowner objections included the fact that Enbridge had failed to negotiate a construction agreement with the landowners that would protect the integrity of the lands affected by the project.

The result?  A complete mess has been made of at least one of the properties involved in the project and it remains to be seen whether the NEB's order will make any difference for future projects.  Will the NEB rethink its relationship with companies like Enbridge?  Will the NEB be as quick to grant land rights to pipeline companies where they have failed to agree on environmental protection measures with landowners? 

Monday, June 23, 2014

CBC Radio Day 6 - Interview with CAEPLA CEO & Director, Dave Core

Coming on the heels of the Federal cabinet's decision to approve the Enbridge Northern Gateway project, CBC Day 6's Brent Bambury interviewed Dave Core, the CEO and Director of CAEPLA (Canadian Association of Energy and Pipeline Landowner Associations).  Listen to Core explain what happens when the land agent comes knocking at: What the pipeline decision could mean for private landowners.

Thursday, June 12, 2014

First Nation granted leave to appeal NEB's Enbridge Line 9B Reversal approval

The Chippewas of the Thames First Nation (COTTFN) has been granted leave to appeal the NEB's approval of the Enbridge Line 9B Reversal and Line 9 Capacity Expansion Project.  The COTTFN had to apply to the Federal Court of Appeal for leave as the first step in its challenge to the NEB decision on the basis that the Federal Crown failed to consult with it over the project.  COTTFN disputes that its participation in the NEB process or public consultation by Enbridge constitutes proper consultation by the Crown.  Read COTTFN's press release on the leave to appeal decision at: FEDERAL COURT OF APPEAL GRANTS CHIPPEWAS LEAVE.

The outcome of the appeal is obviously up in the air, but it is promising to see that COTTFN's arguments about Crown consultation will be heard by the Courts.  Similar arguments were raised by First Nations in the initial Line 9A reversal application hearing, but no appeals were taken from the NEB's approval of that project.  Without an appeal to the Courts, the NEB is left to make the only decisions about whether its own "consultation" process with First Nations fulfills the Crown's obligations.  A conflict of interest? 

Depending on the outcome of the appeal before the Federal Court of Appeal, this may be the kind of case that will go to the Supreme Court of Canada.

Tuesday, June 3, 2014

Enbridge pipelines drive up farm drainage costs

A recent case before the Agriculture, Food and Rural Affairs Appeal Tribunal dealt with a municipal drain affected by three Enbridge pipelines that cross it.  Both the main drain and Branch "A" tiles from the drain cross three Enbridge pipelines (Line 7, Line 8 and Line 9) through manholes that function as siphons.  Siphons are often the only solution (sometimes effective and sometimes not) for the installation and maintenance of tile drains when a pipeline company decides to build through the drainage area. 

The drainage engineer in this situation noted that the siphon reduced capacity in the tiles across the pipelines.  New tiles were to be installed as part of the project under review by the Tribunal; the engineer found that crossing the pipelines at the existing locations would not be feasible without siphons, but that it would be possible to cross underneath the pipelines in higher ground at the "centre location". 

The appeal before the Tribunal dealt with the assessment costs to various landowners.  The engineer had applied a modified "Todgham Method" to calculate the assessments.  He calculated the assessments on the basis of a "natural route" which would have been the assessments if the drains did not have to cross the Enbridge ROW.  He then did a second assessment for the "revised route" based on the presence of the Enbridge ROW and the additional cost to traverse it.  The "natural route" assessment was then modified in conjunction with the "revised route" assessment.

The Tribunal accepted the appeal of one landowner and reduced that landowner's assessment.  The Tribunal found that, in determining the benefit derived by the proposed drainage works to that landowner, it would have been more appropriate for the engineer simply to have made new calculations for the "revised route" rather than modifying the "natural route" calculations (which would not apply because the "revised route" was being used). 

Read the decision at: Re Wakem-Weir Drain.

Wednesday, December 18, 2013

Joint Review Panel Report on Northern Gateway Pipeline to be released on December 19

The Joint Review Panel (NEB) will release its report on the proposed Enbridge Northern Gateway Pipeline on December 19, 2013 at 2:30 Calgary time. 

Wednesday, August 28, 2013

Shippers complain: Does Enbridge have enough insurance?

On May 9, 2011, Enbridge Pipelines (NW) Inc. discovered an oil release near Willowlake Creek, NWT from its Norman Wells Pipeline.  Between 750 and 1,500 barrels (between 119,243 L and 238,485 L) of oil were released.  Enbridge charged repair and clean up costs arising from the spill to its shippers on the pipeline.  One of the shippers, ISH, contacted Enbridge to enquire why insurance coverage on the pipeline was not used to cover the spill costs.  Enbridge did not provide a response.

ISH has now brought a complaint before the National Energy Board (NEB) asking the NEB to compel Enbridge to explain why the spill costs were not paid by insurance and to determine whether Enbridge failed to comply with certain sections of the NEB Act.  In its books, Enbridge designated most of the spill costs as standard costs of operating the pipeline. 

ISH has noted that, at the time of the Norman Wells clean-up, Enbridge may have already exhausted its insurance coverage in dealing with the Line 6B rupture in Marshall, MI.  ISH says that it is "concerned that ENW's insurance coverage, under the comprehensive insurance coverage, had been exhausted at the time of the Pipeline leak, and that ISH, and the other shippers on the Pipeline, were accordingly denied the benefits of insurance coverage."  ISH raises questions about the cross-subsidization of pipelines and its effect on shippers: "exhaustion of insurance by ENW's affiliated entities should not entitle collection of Spill Costs from its shippers, while such Spill Costs would have otherwise been covered by insurance."

Read the complaint at: Letter from ISH to NEB re Enbridge Pipelines (NW) Inc. 2011 Willowlake Pipeline Spill Operating Costs Complaint.