- it is "mindful that Enbridge and parties, who have fully presented their case, are entitled to a timely decision from the Board";
- the NEB "was fully aware that this NTSB report would be issued. Still, the Board commenced its proceeding and conducted a public hearing without waiting for this report.";
- although the NEB has yet to release a decision on the Line 9 Reversal, "the Board is satisfied that it has conducted a comprehensive assessment against its own set of regulatory requirements and applicable Canadian standards to determine whether Enbridge has the ability to safely construct and operate the Project.";
- "The Board is of the view that it has all the information it needs to be able to make a final decision on Enbridge's Project."
Read the decision at: July 20, 2012.